RERA and Bausicht compared
RERA describes delivery requests and day-to-day coordination. Bausicht also describes site area and plan functions.
RERA describes delivery requests and day-to-day coordination. Bausicht also describes site area and plan functions.
This comparison separates published product descriptions from additional self-statements by RERA Logistic. It is not a hands-on test, ranking or price comparison. The relevant distinction is who decides bookings and who needs to edit site areas in the system.
| Criterion | RERA | Bausicht’s vendor claims |
|---|---|---|
| Delivery requests | Contractors and suppliers use the site’s RERA link to request a delivery without an account. Site management accepts, changes or declines the request. RERA product description | Contractors book loading zones and unloading equipment through online delivery notification. The vendor describes one login for delivery notification and area management. Source |
| Shared unloading equipment | Conflict notices for overlapping resource bookings. No automatic conflict resolution (additional self-statement by RERA Logistic). Product limits (German) | Equipment can be assigned to several loading zones; during a reserved slot it is unavailable for other bookings. This is a vendor claim, not a result tested here. Source |
| Editing site areas | No customer plan editor; RERA Logistic helps set up each site (additional self-statement by RERA Logistic). Product limits (German) | Storage areas and loading zones can be drawn or changed in the software. Storage and site setup areas can be adjusted as the project progresses. Source |
| Calendar | Daily project calendar view. RERA Help | A daily and weekly delivery calendar and calendar subscription are described. Source |
Illustrative evaluation scenario: a forklift is needed in the east zone from 09:00–09:45. A second contractor requests 09:15–09:45 in the west zone and needs the same forklift. Next week a storage area must also move. Different zones do not remove the forklift conflict.
Evaluate RERA: site management checks the shared resource in the daily calendar and deals with the conflict. If the forklift is free from 09:45, it can agree on 09:45–10:15 for the second delivery and change the slot. Accepting alone does not move the other booking. For the relocated area, it must ask RERA Logistic what setup can be adjusted; it should not assume a customer plan editor is available.
Evaluate Bausicht: ask the vendor to assign the same forklift to both zones and demonstrate an overlapping booking. Its product description says reserved equipment is unavailable for other bookings. Check how the second contractor then finds a suitable alternative slot. Next, ask for a demonstration of changing the storage area and an explanation of the permissions required. These are evaluation questions based on vendor claims, not observed test results.
Decision in this example: if site management wants to decide each request individually, evaluate that approval workflow. If contractors should book within defined rules and the team should edit areas itself, those Bausicht claims are particularly relevant. A demonstration of both workflows against your project’s needs should guide the choice.
Missing information does not establish that a feature is absent. Ask Bausicht whether a booking can be requested without an account. Check device access and project rules with each provider.
For general preparation, use the delivery checklist.
Bausicht vendor source: Baulogistik Software & Online Avisierungssystem (OAS) (German), checked . The page describes booking loading zones and unloading equipment, preventing double bookings and editing site areas. All Bausicht statements here are vendor claims. Legal notice (German).
RERA sources: product description · project calendar · additional self-statements by RERA Logistic (German). The public product pages do not fully substantiate those additional limits. The date above applies only to the Bausicht vendor-source check, not a new RERA approval.