Spreadsheet delivery planning vs RERA

A spreadsheet may suit a small number of deliveries with one clear owner. RERA brings delivery requests and a day calendar together.

When a spreadsheet is enough

A shared spreadsheet can work when one person owns the agreed schedule and communicates every change. Extra columns are easy to add. The team still has to check that the crane and unloading zone are free together; a simple list does not perform that check.

Worked example: yesterday’s attachment is still circulating

Illustrative example: a façade delivery is scheduled for 10:00–10:45 in the north unloading zone. Work on the access route means site management moves it to 11:00–11:45. The foreman still has yesterday’s spreadsheet attachment showing the old slot.

With the spreadsheet: the owner updates the authoritative file, marks the old slot as superseded and informs the supplier and foreman. Both need to know where to find the current version. A shared file can reduce version confusion, but attachments already sent remain out of date.

With RERA: the request and decision are held in the project. Site management checks resource use for 11:00–11:45 and changes the slot; the requester receives an email notification. The daily calendar supports the site team’s resource check. According to RERA Logistic, conflicts are not resolved automatically: site management must deal with any overlap.

Decision in this example: the spreadsheet remains workable if the foreman uses the authoritative file and changes reliably reach those affected. Consider RERA if requests, decisions and calendar bookings repeatedly have to be reconciled by hand. The supplier still needs to receive and follow the new arrangement.

Criteria for moving from a spreadsheet

  • Does everyone use one authoritative file, or do attachments circulate?
  • Can a deputy distinguish a confirmed slot from a requested one?
  • Who checks the crane and unloading zone together after each change?
  • Which custom columns are essential? Test those requirements in a demonstration rather than assuming the spreadsheet can be replicated.

For the details of an individual delivery, use the delivery checklist. For resource planning, see cranes and unloading zones.

Product sources: RERA: delivery management · RERA Help: project calendar. The stated product limit is an additional self-statement by RERA Logistic.

Request a personal demo   Open the sample project

Read next: Construction delivery management · Construction logistics software